Search

Clean Water Advocacy Newsroom

Clean Water Advocacy - Newsroom - NACWA in the News

States Said to Lack Adequate Resources To Review Analyses Under Blending Plan

States lack the time and money to review the additional analysis that wastewater utilities would have to submit if the Environmental Protection Agency adopts blending guidance drafted jointly by environmental advocates and a utility trade group, state and federal officials say.
At issue is the guidance released Oct. 27 by the Natural Resources Defense Council and the National Association of Clean Water Agencies that EPA is evaluating.

It would require local, state, and federal regulatory agencies to review the detailed rationale that wastewater utilities would be required to offer as part of the permit-renewal process if they want to blend treated and semi-treated wastewater during heavy rains before discharging to lakes and streams (208 DEN A-1, 10/28/05).

States already are struggling to issue National Pollutant Discharge Elimination System permits on a timely basis, according to officials. Adoption of the joint guidance by EPA would place an additional burden on states, some officials said in interviews with BNA and in public comments.

Roberta Savage, the executive director of the Association of State and Interstate Water Pollution Control Administrators, said the agreement was sound but expressed concern about the additional workload states would have to face.

"We do see and anticipate a significant state workload" associated with implementing the agreement, Savage told BNA Oct. 31. "We'll need to take some time to analyze the implications of this agreement on day-to-day implementation of the clean water programs."

Former and current EPA officials, who had hailed the agreement the day it was announced, toned down their initial enthusiasm a day later.

"The approach is reasonable," but states must consider how much funding they have for clean water programs, James Hanlon, director of EPA's wastewater division, told participants Oct. 28 at an American Law Institute-American Bar Association seminar on the Clean Water Act.

Hanlon was on the panel that discussed the "State of the State NPDES Programs" along with Savage and G. Tracy Mehan III, former EPA assistant administrator for water and currently a principal analyst for the Virginia-based Cadmus Group.


Permit-Driven Process Problematic

Mehan agreed with both Hanlon and Savage that the "permit-driven process" would be problematic for states. He said state NPDES programs were getting bogged down by process with little room remaining for innovation. "There is barely enough room for the states to keep their heads above water," Mehan said.
Jon L. Craig, water quality director with Oklahoma's Department of Environmental Quality, objected to the philosophy behind blending as well as the push to place the burden on state agencies.

Blending takes place at treatment plants during heavy rains when the volume of water is more than a plant's capacity can handle. In such cases, a portion of wastewater is rerouted after primary treatment, when solids are removed, around the secondary treatment system and then mixed with treated wastewater and discharged.

"Shifting the burden from cities to states doesn't address the issue of pollution," Craig told BNA Oct. 31. Permitting discharges of raw sewage "just doesn't make sense," he added.

Craig said municipalities have to find solutions to address the problem of raw sewage overflows. In Oklahoma, Craig said, Tulsa and Oklahoma City are in the midst of long-term projects to handle sewer overflows without blending. "That is the way to go," he said.

Oklahoma is one of 44 states that issue their own NPDES permits. According to the most current EPA estimates, 68 percent of NPDES permits are current as of July 31, 2000. In 1998, only 54 percent of permits were current. These permits include those sought by wastewater utilities.

The Clean Water Act specifies that NPDES permits be issued for a five-year term. Permittees that wish to continue discharging beyond the five year limit must reapply at least 180 days prior to the expiration date of their permit.

If the permitting authority receives a complete application, but does not reissue the permit prior to the expiration date, the permit may be "administratively continued." Permits that have been administratively continued beyond their expiration date are considered to be "backlogged," as are those facilities that are awaiting their first NPDES permits, according to EPA.


Reasons for Backlogs Detailed

Hanlon attributed the reasons for a backlog to shortage of trained permit reviewers, shortage of funds, and an abundance of programs requiring permits.
According to Savage, more than half of the money states receive for clean water initiatives are directed toward administering permit programs or grant applications. "What is left is actually spent on actual clean up and restoration projects," she added.

Defending the proposed guidance on blending, NRDC attorney Nancy Stoner said a "detailed analysis is necessary to meet legal requirements if the permitting [agency] wants to authorize anticipated bypasses. It cannot do so without analysis of feasible alternatives."

Anticipated bypasses are an enforcement tool used by regulatory agencies to ensure that wastewater utilities subject wastewater to both primary and secondary treatment processes.

Under current rules, if a wastewater utility expects to skip secondary treatment, a process in which wastewater is passed over bacteria that decompose harmful pathogens and break down organic compounds, then it must inform the regulatory agency and provide a detailed rationale.


Phased Implementation Planned

Consequently, the joint guidance issued by NRDC and NACWA moves the anticipated bypass provision from the enforcement to permitting so that utilities can provide a rationale for the circumstances in which they intend to blend treated and semi-treated wastewater before discharging into lakes, rivers, and streams.
Besides, NACWA senior counsel Alexandra Dunn said, "The lion's share of analysis, including the cost estimates and hiring of engineering consultants, is on the wastewater utility."

The permitting authority has to review the analysis, and only when it is issuing new permits or renewing old ones, she added. "That is why we insisted on a phased implementation rather than having all utilities come forward to have their permits renewed."

The joint agreement between NRDC and NACWA ended months of negotiation to determine when blending would be acceptable. The negotiations began after EPA was forced to shelve its 2003 draft policy in May just hours before House lawmakers threatened to adopt an amendment, barring the agency from expending any resources toward implementing the policy (97 DEN A-1, 05/20/05 ).

EPA's now defunct 2003 draft policy allowed wastewater blending even if there were feasible alternatives. The policy did require utilities to seek a permit, but the utilities were not required to submit a detailed analysis that would be open for public review.

Stoner says the joint draft agreement emphasizes "stronger provisions for monitoring, reporting and public right to know."